Project Dashboard

One screen holding the running projects, ordered by target finish, with physical progress and cost absorption side by side. It carries only what demands action today.

Questions It Answers

Filters

Filter What it does
Start Date Required. The range of project start dates to show. Use a wide range (for example the start of the year until today) to see every running project, then run the report.

How To Read It

Only projects with status Running appear, ordered by Target Finish then project code.

Column Meaning
Project Project code and name.
Target Finish Target finish from the Project master; a dash means it is not filled in.
Physical Progress % From WBS task weights and progress. Zero means the WBS tasks carry no weight yet, or their progress has not been entered.
Cost Absorbed % Total Committed divided by total budget. A dash means that project has no budget yet - not that it has no cost.
Gap Cost Absorbed minus Physical Progress. A positive number is printed bold: cost is running ahead of work. That is the earliest warning a project can give.
Cost Absorbed here already includes material purchased but not yet issued to the project, so the gap does not jump the moment the warehouse issues it.

Why The Numbers May Differ